Forecasting future performance with confidence
Contents |
[edit] The challenge
To report the most likely project outcome with confidence.
Project reporting typically focuses on a single anticipated outcome rather than showing a range of potential outcomes with their associated levels of confidence. Providing a range of potential outcomes with likelihoods:
- Allows early intervention when projects stray off target, thereby increasing the likelihood of a successful outcome.
- Enables potential changes in funding requirements to be identified in a timely manner along with necessary approvals that can then be processed without delaying the project.
While the text below relates to the internal reporting of projects, it could equally be used to report potential project outcomes from supplier to client.
[edit] The idea
Assessing and reporting a project’s most likely financial outcome, as well as best- and worst-case scenarios.
The anticipated project outcome is presented as 'most likely', while also showing the best and worst cases. The most likely, best and worst cases are tracked on a regular basis to provide trends, giving a further level of confidence in the project reporting.
This gives managers and project leaders a quantified perspective on the potential project outcome, which is more tangible and useful than a single forecast outcome or a 'Red, Amber, Green' status. The process is simple and can be readily adopted, with limited training, unlike sophisticated risk analysis insight articles.
[edit] The impact
Better awareness of most likely project outcomes.
Skanska uses the technique to improve the predictability of project outcomes, which in turn helps with business financial forecasting. The approach is used for profitability and cash forecasting at a project and business unit level, giving senior management a better appreciation of a project or business unit’s financial health.
[edit] The barriers to innovation – and the solutions
It is management, not financial, accounting.
Key internal barriers include:
- A high degree of transparency is required in the project life cycle along with trust between senior managers and project teams. Managers and project leaders must not abuse the trust generated by transparent sharing of project performance data.
- Incentivisation, which is linked to the previous point. When setting bonus targets, it is important not to abuse the transparency required for the technique to be effective.
- 'That’s not the way we do things around here' or 'not invented here' mindsets, typical of any change. Strong leadership overcomes this.
- Confusion with strict accounting rules. The use of confidence reporting is part of management accounting and requires judgement and assessment, not simply the strict application of accounting rules.
There are no key external barriers to this approach. As it relates to management accounting it is not governed by strict accountancy rules
[edit] The way forward
Introducing confidence reporting through the use of a pilot, alongside existing reporting systems allows project teams and management to build an understanding of, and confidence in, the process.
A relatively simple process will be required along with training therein. The best results are obtained when the project management team establishes and owns the forecasts, not simply leaving it to the finance team. The finance team must, however, be involved to ensure there is no contradiction with accounting rules.
The approach demands transparency and trust between the project team and those to whom the numbers are being reported. The approach is an art, not a science, and therefore needs people who are not merely slaves to process.
Written by:
Roger Bayliss, Senior Vice-President, Global Operational Efficiency, Skanska, Sweden
This article was originally published on the Future of Construction Knowledge Sharing Platform and the WEF Agenda Blog
Featured articles and news
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.