Forecasting future performance with confidence
Contents |
[edit] The challenge
To report the most likely project outcome with confidence.
Project reporting typically focuses on a single anticipated outcome rather than showing a range of potential outcomes with their associated levels of confidence. Providing a range of potential outcomes with likelihoods:
- Allows early intervention when projects stray off target, thereby increasing the likelihood of a successful outcome.
- Enables potential changes in funding requirements to be identified in a timely manner along with necessary approvals that can then be processed without delaying the project.
While the text below relates to the internal reporting of projects, it could equally be used to report potential project outcomes from supplier to client.
[edit] The idea
Assessing and reporting a project’s most likely financial outcome, as well as best- and worst-case scenarios.
The anticipated project outcome is presented as 'most likely', while also showing the best and worst cases. The most likely, best and worst cases are tracked on a regular basis to provide trends, giving a further level of confidence in the project reporting.
This gives managers and project leaders a quantified perspective on the potential project outcome, which is more tangible and useful than a single forecast outcome or a 'Red, Amber, Green' status. The process is simple and can be readily adopted, with limited training, unlike sophisticated risk analysis insight articles.
[edit] The impact
Better awareness of most likely project outcomes.
Skanska uses the technique to improve the predictability of project outcomes, which in turn helps with business financial forecasting. The approach is used for profitability and cash forecasting at a project and business unit level, giving senior management a better appreciation of a project or business unit’s financial health.
[edit] The barriers to innovation – and the solutions
It is management, not financial, accounting.
Key internal barriers include:
- A high degree of transparency is required in the project life cycle along with trust between senior managers and project teams. Managers and project leaders must not abuse the trust generated by transparent sharing of project performance data.
- Incentivisation, which is linked to the previous point. When setting bonus targets, it is important not to abuse the transparency required for the technique to be effective.
- 'That’s not the way we do things around here' or 'not invented here' mindsets, typical of any change. Strong leadership overcomes this.
- Confusion with strict accounting rules. The use of confidence reporting is part of management accounting and requires judgement and assessment, not simply the strict application of accounting rules.
There are no key external barriers to this approach. As it relates to management accounting it is not governed by strict accountancy rules
[edit] The way forward
Introducing confidence reporting through the use of a pilot, alongside existing reporting systems allows project teams and management to build an understanding of, and confidence in, the process.
A relatively simple process will be required along with training therein. The best results are obtained when the project management team establishes and owns the forecasts, not simply leaving it to the finance team. The finance team must, however, be involved to ensure there is no contradiction with accounting rules.
The approach demands transparency and trust between the project team and those to whom the numbers are being reported. The approach is an art, not a science, and therefore needs people who are not merely slaves to process.
Written by:
Roger Bayliss, Senior Vice-President, Global Operational Efficiency, Skanska, Sweden
This article was originally published on the Future of Construction Knowledge Sharing Platform and the WEF Agenda Blog
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.